K-12 Building Progress - July 2 , 2009
Additional pictures of the building site may be found by clicking on the School Construction Gallery button on the left side of the district home page. Click on any picture to enlarge it. The The K-5 wing and HS wing interior walls are mostly done. Insulation and densglass were installed in the HS wing. HVAC is now being installed in HS classrooms. Most trusses are installed over the classrooms and the plywood roof is being installed now. The media center is being built and is the last tall section to be constructed. Roof shingles are done in the HS and continue to be placed on the roof in the K-5 wing. Block walls are being sanded and the primer coat of paint is being applied. Grass is growing well in the seeded areas and we had our first mowing. Parking lots are being leveled and sidewalks and curbs are being installed in the rear of the school. The finish date continues to be set as April 2010.
|
|
|
|
|
|
|